Power Plant
Client:
Project Type:
Project Start:
Project End:
Status:
TREC
Civil and Building Works for Power Plant
Dec 12, 1996
Dec 23, 1997
Complete
Project Description
Execution of civil and building work associated with the conversion of an existing gas turbine generation station.
The combined cycle addition consisted of: Four head recovery boilers, two steam turbine generators, air-cooled condensers, and water treatment plant
Total work consisted of:
►150,000 cubic meters of earthwork
►1,000 cubic meters of masonry work
►4,000 cubic meters of concrete work
►400 tons of steel work
►20,000 square meters of asphalt paving
►Over 15,000 meters of various pipe work
ARVIN Engineering All Rights Reserved