Cotton Linter Plant

Jan. 8, 1984

June 22, 1986

Complete

ARVIN Engineering All Rights Reserved

Published 2011

 

Project Description

Project involved the erection and full commissioning of plant equipment.  Upon completion of the erection and commissioning, Arvin was responsible for training of client personnel.

1200 pieces of equipment

200 tons auxiliary steel structures

330 tons of stainless steel piping

500 tons of mechanical equipment

150 tons of electrical equipment

20 tons of insulations

10,000 square meter of surface painting