Construction of 56” ROW
IGAT IV - Sec 8 & 9
Construction of 56” ROW
IGAT IV - Sec 8 & 9
Client:
Project Type:
Length:
Project Start:
Project End:
Status:
NIGC
Construction of Right of Way (ROW) for 56” Pipeline
200 Km
Aug 12, 2003
Mar 19, 2004
Complete
Project Description
Seven Million cubic meters of earth excavation, grading of right of way and construction of service road for laying 200 Km of pipeline. Over 45% of the work was carried out in mountainous and rocky terrain.