Water Treatment and Sewage Plant

Home        Projects        Capacity        Contact Us

 

Client:               

Project Type:   


Project Start:   

Project End:    

Status:             

DI

Water Treatment/ Sewage Plant

March 22, 1986

Jan 26, 1988

Complete

ARVIN Engineering All Rights Reserved

Published 2011

 

Project Description

Project involved the installation, erection, and full commissioning of plant equipment.  Upon completion of the erection and commissioning, Arvin was responsible for training of client personnel.

Water treatment capacity of 3 m3/sec

Sewage system capacity of 0.5 m3/sec

2,000 tons of machinery and equipment

700 tons of O.G. and U.G. of CS and SS piping ranging from ½” to 56”

800 tons of mechanical equipment

400 tons of auxiliary steel structures

350 tons of electrical equipment

30 tons of surface painting

Training of client staff