30” Pipeline

Kharmach / Shiraz

Home        Projects        Capacity        Contact Us

 

Client:               

Project Type:

Pipe Dimension:

Pipeline Length:

Project Start:   

Project End:    

Status:             

NIGC

Gas Pipeline

56 Inch Pipe

107 Km

June 2, 2003

Aug 8, 2004

Complete

 

Project Description

The project includes complete civil and mechanical work and full commissioning related to construction of 107 Km high pressure gas transmission of 5LX60 steel polyethylene coated pipeline with the wall thickness varying from 0.469 to 0.625 inches.  The project includes:

32 river, road, flood way and stream crossings

2 launching and receiving trap stations

2 block valve stations

Cathodic protection system including CP stations, test points and line markers

Except for the line pipe, fittings and valves which were supplied by the client, Arvin Engineering was responsible for provision of consumables, welding electrodes, coating materials, CP. materials & equipment and all civil materials.