56” Pipeline
IGAT IV - Sec 6
56” Pipeline
IGAT IV - Sec 6
Client:
Project Type:
Pipe Dimension:
Pipeline Length:
Project Start:
Project End:
Status:
NIGC
Gas Pipeline
56 Inch Pipe
110 Km
Apr 15, 2004
Dec 11, 2004
Complete
Project Description
The project includes partial civil and complete mechanical work and full commissioning related to construction of 110 Km high pressure gas transmission of 5LX70 steel polyethylene coated pipeline with the wall thickness varying from 0.780 to 1.125 inches. The project includes:
►257 river, road, flood way and stream crossings
►1 launching and receiving trap stations
►4 block valve stations
►110 Km of 2” HDPE pipe installed parallel to pipeline for future optical fiber cable
►Cathodic protection system including CP stations, test points and line markers
Except for the line pipe, fittings and valves which were supplied by the client, Arvin Engineering was responsible for provision of consumables, welding electrodes, coating materials, rock shield, CP. materials & equipment and all civil materials.
ARVIN Engineering All Rights Reserved