42” Pipeline
Fajr Refinery
42” Pipeline
Fajr Refinery
Client:
Project Type:
Pipe Dimension:
Pipeline Length:
Project Start:
Project End:
Status:
NIGC
Gas Pipeline
42 Inch Pipe
70 Km
Aug 14, 2005
Dec 9, 2007
Complete
Project Description
The project includes complete civil and mechanical work and full commissioning related to construction of 70 Km high pressure sour gas transmission of 5LX65 steel polyethylene coated pipeline with the wall thickness varying from 0.688 to 0.935 inches. The project includes:
►50 river, road, flood way and stream crossings
►2 launching and receiving trap stations
►12 line brake valve stations
►Installation of fiber optic cable
►Cathodic protection system including CP stations, test points and line markers
Except for the line pipe, fittings, valves, CP materials and consumables such as welding electrodes and coating material which were supplied by the client, Arvin Engineering was responsible for provision of rock shield, geotextile and all civil materials.
ARVIN Engineering All Rights Reserved