56” Pipeline

IGAT VIII - Sec 4

Home        Projects        Capacity        Contact Us

 

Client:               

Project Type:

Pipe Dimension:

Pipeline Length:

Project Start:   

Project End:    

Status:             

NIGC

Gas Pipeline

56 Inch Pipe

206 Km

Dec 19, 2006

Jan 5, 2010

Complete

 

Project Description

The project includes complete civil and mechanical work and full commissioning related to construction of 206 Km high pressure gas transmission of 5LX70 steel polyethylene coated pipeline with the wall thickness varying from 0.780 to 1.125 inches.  The project includes:

68 river, road, flood way and stream crossings

3 launching and receiving trap stations

5 line brake valve stations

Installation of fiber optic cable

Cathodic protection system including CP stations, test points and line markers

Except for the line pipe, fittings and valves which were supplied by the client, Arvin Engineering was responsible for provision of consumables, welding electrodes, coating materials, rock shield, CP. materials & equipment and all civil materials.