Steel Mill Plant
Client:
Project Type:
Project Start:
Project End:
Status:
NISCO
Steel Mill Plant
Aug 22, 1988
Nov 6, 1991
Complete
Project Description
Installation, erection, and cold commissioning of steel mill plant.
Mechanical and electrical installation, cold commissioning of
►Approximately 24,000 tons of equipment.
►3,500 tons of auxiliary steel structure
►3,800 tons piping O.G. and U.G. ranging from ½” to 40”
►10,000 tons of mechanical equipment
►2,500 tons of electrical equipment
►3,200 tons of refractories
►Over 1,000 Km cabling
►150,000 square meters of surface painting
ARVIN Engineering All Rights Reserved